Case Studies
London Road Project
The Results
This project highlights CLC’s ability to deliver high-risk, high-complexity infrastructure works while maintaining supply continuity on major water assets. Through strong planning, innovative engineering, and collaborative delivery, CLC ensured customer protection, operational continuity, and a safe, high-quality outcome.
The Challenge

Affinity Water identified a failed valve on a strategic 800mm trunk main supplying a large section of their network.
Failure to address the issue quickly risked severe service disruption, potentially affecting tens of thousands of properties.
CLC was engaged to:
-
Assess the condition of the asset
-
Work collaboratively with Affinity Water to design a solution
-
Enable repairs without shutting down the main, ensuring continuous supply
-
Overcome significant site access and operational constraints in a rural environment
The Solution
Installation of 450mm bypass system spanning over 200 metres.

Installed 1km of 900mm large diameter rising sewage mains.


Excavation work completed at a depth of 6.5m up to 2.5m.

Installed 200m of 450mm

Water management aligned to EA requirements, despite overflowing watercourse adjacent to the works.
The Results
The project reached completion on the section of works in a safe and timely manner.
-
Zero impact to customers — the network remained live and pressurised for the entire duration
-
The faulty 800mm valve was successfully replaced, restoring full operational control of this strategic asset
-
Delivered injury-free and incident-free, supported by robust process controls and modern risk-management technology
-
All reinstatement completed to a high standard, receiving successful acceptance from the landowner
-
Demonstrated strong collaboration between CLC, Affinity Water, and key supply chain partners
Services covered
Environmentally-conscious, safe & efficient back-fill and reinstatement works, driven by innovation and outstanding customer experience.
Smart maintenance and repair services, responding rapidly to planned and emergency situations with unparalleled levels of expertise, efficiency, and value.
Temporary relocation or alternations to existing infrastructure to protect assets and minimise service disruption.
Supporting long-term projects to improve, build, or maintain services, crafting strategies that enhance utilities with care for the environment.
Single contractor services for water, gas, electric, and telecoms infrastructure to service developments and communities.
An industry-leading complete solution for upgrading small sections to larger footprints of your existing network.
Competitively priced meter fitting and Pressure Release Valve installation works, without compromising on high standards of customer service.
Construction, connection and commissioning of new Water, Gas or Electric infrastructure to support new or existing network demand.